		<title>
			THERMAL POWER PROJECT EXPERIENCE
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/THERMAL%20POWER%20PROJECT%20EXPERIENCE" />
		

		<id>@wiki::24/</id>
		<published>
			2007-03-22
			
		</published>
		<updated>
			2007-03-22T09:35:39Z
		</updated>
		
		
				
		<summary>
			**LARGEST PROJECT EXPERIENCE

The Largest Project I have worked is 210 plus 210 Megawatts Pipri Thermal Power Station Unit 1&amp; 2 with all its infra structures including one Bridge, roads, Sea Water Intake Channel, Sea Water Pump House, Turbine House &amp; TG foundation, Switch Gear Buildings (220kv, 132kv &amp; 11kv), Raw Water Basin, Fuel Tank Foundations, Administration Block, Canteen, Helipads, Workshop, RCC Underground &amp; Overhead Cable Ducts, Leveling &amp; Grading, Land Escaping &amp; External Development, Boundary Wall, Gate Houses, and many small structures, in fact a big Structure Complex.
I have carried out all post tender Contract Administration &amp; Estimating functions including Finalization the Huge Project Independently. My Responsibility on this project all Quantity Surveying &amp; Estimating functions including preparation, submission &amp; getting approval of Interim &amp; Final bills, preparation, submission &amp; getting approval of Claims &amp; Extra Items, timely advising project manager regarding Contractual Obligations, preparation, submission &amp; getting approval of all Finalization Documents, preparation, submission &amp; getting approval of Variation Orders, preparation, submission &amp; getting approval of Bar Bending Schedule, preparation of Ordinary &amp; Specialist Sub Contracts, Takeoff of all Earth Works, Sub Structures, Super Structures, Finishes, Steel bars, Steel Structures, Bridge, Roads &amp; other ancillary structures, Computing &amp; Indenting Construction Materials, Checking &amp; Advising Corrections in Execution Drawings, Organizing preparation of As Built Drawings, Initiating all Contractual Correspondence including correspondence regarding Extension of Time, and other routine Quantity Surveying and Estimating functions.**
		</summary>
	</entry>
		<entry>
		<title>
			MY RECENT EXPERIENCE OF 4 AIRPORTS
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/MY%20RECENT%20EXPERIENCE%20OF%204%20AIRPORTS" />
		

		<id>@wiki::23/</id>
		<published>
			2007-03-22
			
		</published>
		<updated>
			2007-03-22T09:32:54Z
		</updated>
		
		
				
		<summary>
			**RECENT EXPERIENCE

My most recent experience is FOUR AIRPORT PROJECTS in series, including Mary Airport Turkmenistan. 
DUTIES PERFORMED: Responsible for all Quantity Surveying &amp; Estimating functions including Post-tender Contract Administration, preparation submission &amp; getting approval of Interim &amp; Final Bills, preparation submission &amp; getting approval of Claims &amp; Extra Items, timely advising project manager regarding Contractual Obligations, preparation submission &amp; getting approval of all Finalization Documents including Contract Closeout Documents, preparation submission &amp; getting approval of Variation Orders, Preparation of Bar Bending Schedule, Preparation of ordinary &amp; Specialist Sub Contracts, Takeoff of quantities for billing &amp; progress reports, Computing &amp; Indenting Construction Materials, Checking &amp; advising Corrections in Execution Drawings, Organizing preparation of As built Drawings, initiating all Contractual Correspondence and other routine Quantity Surveying &amp; Estimating functions.**
		</summary>
	</entry>
		<entry>
		<title>
			MEMBERSHIPS
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/MEMBERSHIPS" />
		

		<id>@wiki::22/</id>
		<published>
			2007-03-22
			
		</published>
		<updated>
			2007-03-22T09:30:43Z
		</updated>
		
		
				
		<summary>
			**MEMBERSHIPS

1: Sindh Bar Council: Advocate on roll since July 2002.
2: Institute of Engineers, Pakistan: Student Member Since July 1977 in the faculty of Civil Engineering.**
		</summary>
	</entry>
		<entry>
		<title>
			MY COVER NOTE
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/MY%20COVER%20NOTE" />
		

		<id>@wiki::21/</id>
		<published>
			2007-03-21
			
		</published>
		<updated>
			2007-03-21T15:26:07Z
		</updated>
		
		
				
		<summary>
			**Dear Sir,

As a Quantity Surveyor, Contract Administrator (Pre-Contract &amp; Post-Contract) &amp; Estimator having  over 30 years of extensive experience, I have developed my skills in all Estimating Functions, by continually increasing my academic &amp; professional qualifications, and by initiating in all quarters of this field. I am known for my accuracy &amp; meeting deadlines in difficult conditions.
Having a Master’s Degree in Law (viva remaining), a Student Membership in the Institute of Engineers( Civil Engineering ) &amp; a Commerce Graduate, I am still eager to increase my professional qualifications by on line education especially from Royal Institute of Chartered Surveyors.
My interest in the position of a job opening has prompted me to upload my Resume on my website for your consideration.
I would like to be part of an organization that offers stability, potential growth &amp; advancement opportunities. I am sure that my extensive experience &amp; high qualifications would be a great asset to your company. My recent experience in pre-tender &amp; post-tender Contract Administration &amp; Finalization of 4 Airport Projects in series including one of Mary Airport Turkmenistan, would definitely complement your Company’s projects.
I have a record of outstanding success in the Finalization of Contracts with International Clients and Consultants, in Multinational &amp; International Environments. I have received several commendations for my dedication &amp; professionalism, and continuously received recognition for my communication skills leadership excellence.
Based on my qualifications &amp; experiences, I believe I am the right person to oversea the delivery of Quantity Survey for your projects.
The enclosed Resume is a brief summary of my qualifications &amp; my experiences. I would be delighted to provide you further details as and when required. My Resume is a good summary of my background &amp; general experience however I would like to provide more details when required. I would like a chance to convince you that my skills and energy would be an asset to your Organization.
Thank you in advance for your generous consideration. I may be reached at my mobile number shown in Resume attached, (00923452746330) should you desire to contact me. I would be happy to myself available for a telephone interview at your convenience.

Regards,  

M. A. Nafees Kazmi**
		</summary>
	</entry>
		<entry>
		<title>
			REFERENCES
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/REFERENCES" />
		

		<id>@wiki::20/</id>
		<published>
			2007-03-20
			
		</published>
		<updated>
			2007-03-20T19:34:56Z
		</updated>
		
		
				
		<summary>
			REFERENCES

1: MR. WAHEED MUGHAL: Manager Contracts-Ashfaq Associates (Private) Limited. Immediate Boss.
Mobile: 00923213771733
E-mail:  aapl@gerrys.net

2: MR. ALI HASSAN RIZVI: Director &amp; CFO- MacDonald Layton &amp; Company Limited. Ex-Boss.
Mobile: 00923452387883
E-mail:  finance.mlgroup@yahoo.com

3: BRIGADIER NASIRUDDIN HUMAYOON: Chairman- MacDonald Layton &amp; Company Limited. Ex-Boss.
Phone:  0092214560149
E-mail:  finance.mlgroup@yahoo.com
		</summary>
	</entry>
		<entry>
		<title>
			MY CAREER LEVEL &amp; TARGET JOB
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/MY%20CAREER%20LEVEL%20%2526%20TARGET%20JOB" />
		

		<id>@wiki::19/</id>
		<published>
			2007-03-20
			
		</published>
		<updated>
			2007-03-20T19:33:18Z
		</updated>
		
		
				
		<summary>
			CAREER LEVEL

Career Level: Management
Notice Period: 2 weeks   
Last Salary: US$ 8,000.00 per annum

TARGET JOB

Job Location: Anywhere
Job Category: Quantity Survey, Construction, and Consulting Services.
Employment Type: Any
		</summary>
	</entry>
		<entry>
		<title>
			MY PROJECTS
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/MY%20PROJECTS" />
		

		<id>@wiki::18/</id>
		<published>
			2007-03-20
			
		</published>
		<updated>
			2007-03-20T19:28:58Z
		</updated>
		
		
				
		<summary>
			RECENT EXPERIENCE

My most recent experience is FOUR AIRPORT PROJECTS in series, including Mary Airport Turkmenistan. 
DUTIES PERFORMED: Responsible for all Quantity Surveying &amp; Estimating functions including Post-tender Contract Administration, preparation submission &amp; getting approval of Interim &amp; Final Bills, preparation submission &amp; getting approval of Claims &amp; Extra Items, timely advising project manager regarding Contractual Obligations, preparation submission &amp; getting approval of all Finalization Documents including Contract Closeout Documents, preparation submission &amp; getting approval of Variation Orders, Preparation of Bar Bending Schedule, Preparation of ordinary &amp; Specialist Sub Contracts, Takeoff of quantities for billing &amp; progress reports, Computing &amp; Indenting Construction Materials, Checking &amp; advising Corrections in Execution Drawings, Organizing preparation of As built Drawings, initiating all Contractual Correspondence and other routine Quantity Surveying &amp; Estimating functions.

LARGEST PROJECT EXPERIENCE

The Largest Project I have worked is 210 plus 210 Megawatts Pipri Thermal Power Station Unit 1&amp; 2 with all its infra structures including one Bridge, roads, Sea Water Intake Channel, Sea Water Pump House, Turbine House &amp; TG foundation, Switch Gear Buildings (220kv, 132kv &amp; 11kv), Raw Water Basin, Fuel Tank Foundations, Administration Block, Canteen, Helipads, Workshop, RCC Underground &amp; Overhead Cable Ducts, Leveling &amp; Grading, Land Escaping &amp; External Development, Boundary Wall, Gate Houses, and many small structures, in fact a big Structure Complex.
I have carried out all post tender Contract Administration &amp; Estimating functions including Finalization the Huge Project Independently. My Responsibility on this project all Quantity Surveying &amp; Estimating functions including preparation, submission &amp; getting approval of Interim &amp; Final bills, preparation, submission &amp; getting approval of Claims &amp; Extra Items, timely advising project manager regarding Contractual Obligations, preparation, submission &amp; getting approval of all Finalization Documents, preparation, submission &amp; getting approval of Variation Orders, preparation, submission &amp; getting approval of Bar Bending Schedule, preparation of Ordinary &amp; Specialist Sub Contracts, Takeoff of all Earth Works, Sub Structures, Super Structures, Finishes, Steel bars, Steel Structures, Bridge, Roads &amp; other ancillary structures, Computing &amp; Indenting Construction Materials, Checking &amp; Advising Corrections in Execution Drawings, Organizing preparation of As Built Drawings, Initiating all Contractual Correspondence including correspondence regarding Extension of Time, and other routine Quantity Surveying and Estimating functions.






LIST OF PROJECTS WHERE WORKED.

1: MARY AIRPORT, TURKMENISTAN.
Dates: April-2005 to July-2006.
Company Name: Ashfaq Associates (Private) Limited &amp; Al Jawahir Technical Pakistanian Contracting Company LLC, Abu Dhabi. (JV Consultant &amp; Contractor)
Project: Airport. (New Rigid Runway, Taxiways &amp; Apron including AGL &amp; ILS for CAT-3 Type for Boeing 747-400)
Position: Senior Quantity Surveyor. (Post-contract Contract Administration including Finalization)
DUTIES PERFORMED: Responsible for all Quantity Surveying &amp; Estimating functions including Post-tender Contract Administration, preparation submission &amp; getting approval of Interim &amp; Final Bills, preparation submission &amp; getting approval of Claims &amp; Extra Items, timely advising project manager regarding Contractual Obligations, preparation submission &amp; getting approval of all Finalization Documents, preparation submission &amp; getting approval of Variation Orders, Preparation of Bar Bending Schedule, Preparation of ordinary &amp; Specialist Sub Contracts, Takeoff of quantities for billing &amp; progress reports, Computing &amp; Indenting Construction Materials, Checking &amp; advising Corrections in Execution Drawings, Organizing preparation of As built Drawings, initiating all Contractual Correspondence and other routine Quantity Surveying &amp; Estimating functions.
Cost: US $ 24 million.
Client: Department of President’s Affairs, Abu Dhabi.
Project Managers: EC HARRIS, Abu Dhabi.

2: BAHAWALPUR AIRPORT, Pakistan. (Terminal Building, Royal Lounge, Parking &amp; External Development)
Dates: August-2006 to March-2007
Company Name: Ashfaq Associates (Private) Limited. (Consultant &amp; Contractor)
Project: Airport. (Terminal Building, Royal Lounge, Parking &amp; External development)
Position: Senior Quantity Surveyor. (Pre-contract Administration including Participation at Designing stage. And Post-contract Contract administration including Finalization of Contract) 
Cost: US $ 2.5 million.
Client: Dubai Civil Aviation Authority- DCA

3: ROJHAN MEDICAL HOSPITAL, Rojhan, Pakistan.
Dates: February-2006 to July-2006.
Company Name: Ashfaq Associates (Private) Limited. (Consultant &amp; Contractor)
Project: 40 Bed Hospital including Equipment.
Position: Senior Quantity Surveyor. (Site Quantity Survey functions)
Cost: US $ 2.85 million

4: PESHAWER AIRPORT, Pakistan. (Up Gradation of Flexible Runway, Taxiway &amp; Semi-rigid Apron, and New Flexible Taxiway)
Dates: November-2003 to March- 2005.
Company Name: Ashfaq Associates (Private) Limited. (Consultant &amp; Contractor)
Project: Airport. (Up Gradation of Flexible Runway, Taxiway &amp; Semi-rigid Apron, and New Flexible Taxiway including AGL for Boeing 747-400)
Position: Senior Quantity Surveyor. (Pre-contract Contract Administration including active participation in Pre-contract Negotiation Meetings. And Post-contract Contract Administration including Finalization of Contract). 
DUTIES PERFORMED: Responsible for all Quantity Surveying &amp; Estimating functions including Pre-contract &amp; Post-contract Contract Administration, preparation submission &amp; getting approval of Interim &amp; Final Bills, preparation submission &amp; getting approval of Claims &amp; Extra Items, timely advising project manager regarding Contractual Obligations, preparation submission &amp; getting approval of all Finalization Documents including Contract Closeout Documents, preparation submission &amp; getting approval of Variation Orders, Preparation of Bar Bending Schedule, Preparation of ordinary &amp; Specialist Sub Contracts, Takeoff of quantities for billing &amp; progress reports, Computing &amp; Indenting Construction Materials, Checking &amp; advising Corrections in Execution Drawings, Organizing preparation of As built Drawings, initiating all Contractual Correspondence and other routine Quantity Surveying &amp; Estimating functions.
Cost: US $ 4.5 million.
Client: Dubai Civil Aviation Authority- DCA

5: BAHAWALPUR AIRPORT, Pakistan. (New Flexible Runway &amp; Taxiway, and New Rigid Apron including AGL for Boeing 737)
 Dates: September-2002 to April-2003.
Company Name: Ashfaq Associates (Private) Limited. (Consultant &amp; Contractor)
Project: Airport. (New Flexible Runway &amp; Taxiway, and New Rigid Apron including AGL CAT-1 for Boeing 737)
Position: Senior Quantity Surveyor. (Post-contract Contract Administration including Finalization of Contract)
DUTIES PERFORMED: Responsible for all Quantity Surveying &amp; Estimating functions including Post-contract Contract Administration, preparation submission &amp; getting approval of Interim &amp; Final Bills, preparation submission &amp; getting approval of Claims &amp; Extra Items, timely advising project manager regarding Contractual Obligations, preparation submission &amp; getting approval of all Finalization Documents including Contract Closeout Documents, preparation submission &amp; getting approval of Variation Orders, Preparation of Bar Bending Schedule, Preparation of ordinary &amp; Specialist Sub Contracts, Takeoff of quantities for billing &amp; progress reports, Computing &amp; Indenting Construction Materials, Checking &amp; advising Corrections in Execution Drawings, Organizing preparation of As built Drawings, initiating all Contractual Correspondence and other routine Quantity Surveying &amp; Estimating functions.
Cost: US $ 6.5 million.
Client: Dubai Civil Aviation Authority- DCA

6: RAHIMYARKHAN AIRPORT, Pakistan. (Up Gradation &amp; Widening of Flexible Runway, New Rigid Dumb-bells, Extention of Rigid Apron including AGL for Boeing 747)
Dates: July-2002 to August-2002.
Company Name: Ashfaq Associates (Private) Limited. (Consultant &amp; Contractor)
Project: Airport. (Up Gradation &amp; Widening of Flexible Runway, New Rigid Dumb-bells, Extention of Rigid Apron including AGL for Boeing 747)
Position: Senior Quantity Surveyor. (Preparation of Interim Bills &amp; other project Quantity Survey functions)
Cost: US $ 12.5 million.
Client: Department of President’s Affairs, Abu Dhabi.

 7: MATEEN HEAVEN, Karachi, Pakistan.
Company Name: Mateen Builders.
Project: Residencial Appattments.
Position: Worked on Job Basis. (Preparation &amp; Finalization of Sub Contractor’s Bills)


8: MATEEN GALAXY, Karachi, Pakistan.
Company Name: Mateen Builders.
Project: Shopping Center.
Position: Worked on Job Basis. (Preparation &amp; Finalization of Sub Contractor’s Bills)

9: MATEEN MALL, Karachi, Pakistan.
Company Name: Mateen Builders.
Project: Residencial Appattments.
Position: Worked on Job Basis. (Preparation &amp; Finalization of Sub Contractor’s Bills)

10: MATEEN CENTER, Karachi, Pakistan.
Company Name: Mateen Builders.
Project: Shopping Center.
Position: Worked on Job Basis. (Preparation &amp; Finalization of Sub Contractor’s Bills)

11: MATEEN SHOPPING CENTER, Karachi, Pakistan.
Company Name: Mateen Builders.
Project: Shopping Center.
Position: Worked on Job Basis. (Preparation &amp; Finalization of Sub Contractor’s Bills)

12: MATEEN ARCADE, Karachi, Pakistan.
Company Name: Mateen Builders.
Project: Residencial Appattments.
Position: Worked on Job Basis. (Preparation &amp; Finalization of Sub Contractor’s Bills)

13: MATEEN COMPLEX, Karachi, Pakistan.
Company Name: Mateen Builders.
Project: Residencial Complex.
Position: Worked on Job Basis. (Preparation &amp; Finalization of Sub Contractor’s Bills)

14: WESTERN RESTAURANT, Karachi, Pakistan.
Company Name: Murtazvi Builders.
Project: An advance Restaurant like KFC.
Position: Worked on Job Basis. (Preparation of Final Bill by Physical Measurements)

15: WESTERN RESTAURANT, Clifton, Karachi, Pakistan.
Company Name: Murtazvi Builders.
Project: An A-Class Restaurant like KFC.
Position: Worked on Job Basis. (Preparation of Final Measurements of Civil Works by Physical Measurements)

16: BOHRI JAMAT KHANA SADDAR, Karachi, Pakistan.
Company Name: Murtazvi Builders.
Project: A Mosque &amp; Community Center.
Position: Worked on Job Basis. (Preparation of Final Measurements by Physical Measurements)



17: POTABLE WATER SUPPLY WORKS, Karachi, Pakistan.
Company Name: Murtazvi Builders.
Project: Water Supply Works.
Position: Worked on Job Basis. (Estimation for tender of the said works)
Cost: US $ 25 million

18: PSO HOUSE, Karachi, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: A Commercial Building of Pakistan State Oil (PSO)
Position: Senior Quantity Surveyor (Post-contract Contract Administration upto all structure works. Subsequently the matter had gone in dispute and referred to Sole Arbitrator. I assisted the legal counsel during the whole process of Arbitration and finally won the suit with execution of huge compensation of US $ 0.35 million.
Cost: US $ 6.7 million.

19: RAFHAN MAIZE PRODUCTS FACTORY (A sister firm of KNORR USA), Bhai Pheroo, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor
Project: A Factory of Maize Products.
Position: Senior Quantity Surveyor (Contract Administration &amp; Finalization)
Cost: US $ 2.5 million.

20: AYUB MEDICAL COLLEGE &amp; HOSPITAL, Abottabad, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: Medical College &amp; Hospital.
Position: Senior Quantity Surveyor. 

21: MARDAN SALINITY CONTROL &amp; RECLAIMATION PROJECT, Mardan, Pakistan. 
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: Salinity control &amp; reclaimation project.
Position: Senior Quantity Surveyor.
Cost: US $ 7.6 million.

22: NATIONAL ASSEMBLY ISLAMABAD, Islamabad, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: National Assembly of Pakistan at Islamabad.
Position: Senior Quantity Surveyor.
Cost: US $ 12.6 million.

23: AGRICULTURAL DEVELOPMENT BANK of PAKISTAN, Islamabad, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: Head Office &amp; commercial building of ADBP.
Position: Senior Quantity Surveyor.
Cost: US $ 2.45 million




24: NDFC- NATIONAL DEVELOPMENT FINANCE CORPORATION, Karachi, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: Commercial Building of NDFC.
Position: Senior Quantity Surveyor.
Cost: US $ 1.5 million.

25: PANGRIO SUGAR MILL, Pangrio, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: Sugar mill.
Position: Senior Quantity Surveyor. (Interim Bills &amp; Finalization of Contract)
Cost: US $ 2.1 million.

26: ABADGAR SUGAR MILL, Abadgar Sindh, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: Sugar mill.
Position: Senior Quantity Surveyor. (Interim Bills &amp; Finalization of Contract)
Cost: US $ 2.7 million.

27: USMAN SUGAR MILL, Khairpur, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: Sugar mill.
Position: Senior Quantity Surveyor. (Interim Bills &amp; Finalization of Contract)
Cost: US $ 1.65 million.

28: HOTEL HOLIDAY INN (Now MARRIOT), Karachi, Pakistan.
Developer Name: Hashwani Sales.
Project: 5 Star Hotel.
Position: Takeoff of Civil Works on Contract Basis.

29: HOTEL INN, Karachi Airport, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: A Motel Type Hotel at Airport especially for pilots &amp; airhostesses.
Position: Senior Quantity Surveyor.

30: PAKISTAN SECURITY PRINTING PRESS, Karachi, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: Currency notes &amp; stamps printing press.
Position: senior Quantity Surveyor.


31: PIPRI THERMAL POWER STATION UNIT 1 &amp; 2, Karachi, Pakistan.
Company Name: MacDonald Layton &amp; Company Limited (British Management)
Company Status: Contractor.
Project: The Largest Project I have worked is 210 plus 210 Megawatts Pipri Thermal Power Station Unit 1&amp; 2 with all its infra structures including one Bridge, roads, Sea Water Intake Channel, Sea Water Pump House, Turbine House &amp; TG foundation, Switch Gear Buildings (220kv, 132kv &amp; 11kv), Raw Water Basin, Fuel Tank Foundations, Administration Block, Canteen, Helipads, Workshop, RCC Underground &amp; Overhead Cable Ducts, Leveling &amp; Grading, Land Escaping &amp; External Development, Boundary Wall, Gate Houses, and many small structures, in fact a big Structure Complex.
Position: As Senior Quantity Surveyor, I have carried out all post tender Contract Administration &amp; Estimating functions including Finalization the Huge Project Independently. My Responsibility on this project was all Quantity Surveying &amp; Estimating functions including preparation, submission &amp; getting approval of Interim &amp; Final bills, preparation, submission &amp; getting approval of Claims &amp; Extra Items, timely advising project manager regarding Contractual Obligations, preparation, submission &amp; getting approval of all Finalization Documents, preparation, submission &amp; getting approval of Variation Orders, preparation, submission &amp; getting approval of Bar Bending Schedule, preparation of Ordinary &amp; Specialist Sub Contracts, Takeoff of all Earth Works, Sub Structures, Super Structures, Finishes, Steel bars, Steel Structures, Bridge, Roads &amp; other ancillary structures, Computing &amp; Indenting Construction Materials, Checking &amp; Advising Corrections in Execution Drawings, Organizing preparation of As Built Drawings, Initiating all Contractual Correspondence including correspondence regarding Extension of Time, and other routine Quantity Surveying and Estimating functions.

32: NATIONAL FIBRES POLYESTER PROJECT, Karachi, Pakistan.
Company Name: Zor Engineers Limited (British management)
Project: A project for preparation of polyester fibres for fabrics.
Posotion: Quantity Surveyor.
RESPONSIBILITIES
01: Preparation Submission &amp; getting Approval Interim Bills.
02: Preparation, Submission &amp; getting Approval Claims and Extra Items.
03: Preparation &amp; getting Approval of steel Bar Bending Schedule.
04: Drafting Contractual Correspondence.
05: Computing &amp; Indenting Construction Materials.
06: Take off &amp; Estimation of Industrial Projects, Over head Tanks, Offices, Residential Buildings, Sports Complex, 
07: Computing &amp; Indenting Construction Materials.
08: Preparation of Sub-Contracts.
09: Preparation of Sub-Contractor’s Bills. 
10: Preparation of Bill of Quantities.
11: Other routine Quantity Surveying Functions.
Cost: US $ 2.5 million.

33: CANTEEN AT PAKISTAN STEEL MILL, Karachi, Pakistan. 
Dates: June-1976 to December-1976.
Company Name: Gulzar Builders
Project: Canteen.
Position: Quantity Surveyor.
Cost: US $ 0.65 million.

34: SHAHNAWAZ BHUTTO MEMORIAL LIBRARY &amp; JEALOUS BAZAAR, Larkana, Pakistan.   
Dates: November-1975 to May-1976
Company Name: ASAN Associates (Consultants)
Project: Library &amp; Bazaar.
Position: Quantity Surveyor &amp; Site Incharge.
Cost: US $ 0.5 million





35: SEA BREEZE APARTMENTS, Karachi, Pakistan.
Dates: May-1975 to October-1975.
Company Name: Chawla Construction Company. (Builder, Developer)
Project: Residential Apartments.
Position: Trainee Supervisor.
Cost: US $ 1 million.
		</summary>
	</entry>
		<entry>
		<title>
			MY SKILLS &amp; LANGUAGES
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/MY%20SKILLS%20%2526%20LANGUAGES" />
		

		<id>@wiki::17/</id>
		<published>
			2007-03-20
			
		</published>
		<updated>
			2007-03-20T19:27:00Z
		</updated>
		
		
				
		<summary>
			SKILLS

01: MS Word: Beginner with 6 months experience &amp; currently using.
02: MS Excel: Beginner with 6 months experience &amp; currently using.
03: AutoCAD: Beginner with 3 months experience &amp; currently using.
04: Internet Browsing &amp; Mail Management: Beginner with 6 months experience &amp; currently using.
05: Primavera: Beginner with 2 months experience &amp; currently learning.
06: Pre-tender Contract Administration: Intermediate with 3 years Experience including two Airports. Last used 2-year back.
07: Post-tender Contract Administration: Expert with 20 years experience including Four Airports in series during the past 5 years including one Turkmenistan. Currently using.
08: Active participation in Pre-Contract Negotiation-Intermediate with experience of 3 years. Last used 2 years back. 
09: Preparation Submission &amp; getting Approval Interim &amp; Final Bills. Expert with experience of more than 10 years. Currently using.
10: Preparation Submission &amp; getting Approval of Claims &amp; Extra Items. Expert with more than 5 years. Currently using.
11:Timely advising project directors &amp; managers, actions regarding Contractual Obligations. Expert with experience of more than 5 years. Last used one-year back.
12: Preparation, Submission &amp; getting Approval of all Finalization Documents including Contract Close Out Documents. Intermediate with experience of more than 3 years. Last used about one year back.
13: Preparation, Submission &amp; getting Approval of Variation Orders. Expert with experience of more than 5 years. Currently using.
14: Preparation &amp; getting Approval of Bar Bending Schedule. Intermediate with experience of more than 5 years. Last used 2 years back.
15: Preparation of Ordinary &amp; Specialist Sub-Contracts. Intermediate with experience of more than 2 years. Last used 6 months back.
16: Preparation of Contract Documents. Intermediate with experience of more than 3 years. Last used 2 years back.
17: Take Off &amp; Estimating from Conceptual &amp; Working Drawings. Expert with experience of more than 10 years. Currently using.
18: Take for billing purpose of Airport Projects, Runways, Taxiways, Aprons, Terminal Buildings, Royal Lounges, Parking &amp; External Developments, Up gradations of Runways, Taxiways &amp; Aprons, Hangers, Palaces, Garages, Residential Complexes, Hospitals, Thermal Power Project, Security Printing Press, Sugar Mills, Embassy, Commercial Buildings, Sports Complex, Helipads, Salinity Control &amp; Reclamation project, Roads, Bridge, Shopping Centers, Restaurants, Industrial Projects, Residential Complexes, Hospitals,  5-Star Hotel. Expert with experience of more than 10 years. Currently using.
19: Takeoff &amp; Estimation of Refurbishment Works, Addition &amp; Alteration Works. Intermediate with experience of more than 2 years. Last used 3 months back.
20: Calculating &amp; Indenting Construction Materials. Expert with experience of more than 6 years. Last used 3 months back.
21: Checking &amp; Advising Corrections in Working / Execution Drawings. Expert with experience of more than 3 years. Last used 4 months back.
22: Take off &amp; Estimation of Furniture’s &amp; Interiors. Intermediate with experience of more than 2 years. Last used 2 months back.
23: Organizing Preparation of As built Drawings. Expert with experience of more than 2 years. Last used 2 months back.
24: Drafting &amp; initiating all Contractual Correspondence. Expert with experience of more than 5 years. Last used 6 months back.
25: Drafting letter for Extension of Time. Expert with experience of more than 2 years. Last used 2 years back.
26: Participating in Design of Airport Projects. Intermediate with experience of more than one year. Last used 2 years back.
27: Reconciliation of Materials. Expert with more than 5 years experience. Last used 3 years back.
28: Reconciliation of Labor. Intermediate with experience of more than 2 years. Last used 6 years back.
29: Assisting Arbitration in Civil Engineering Contracts. Intermediate with 3 years experience. Last used 6 years back.
30: Communication skills. Intermediate advanced level, with experience of more than 5 years.

LANGUAGES

1: ENGLISH: Can Read, Write &amp; Speak Conversion ally. All Education &amp; Practical Experiences are in English Language through out. Intermediate level having practiced for more than 10 years. Currently using.
2: URDU: Expert being mother tongue.
3: FARSI (Persian): Intermediate level. Practiced for more than two years. Last used one-year back.
4: RUSSIAN: Beginner level. Practiced for about one year. Last used one-year back.
5: HINDI: Can speak and understand. 
6: ARABIC: Beginner level. Can read &amp; write. Speaking is weak.
		</summary>
	</entry>
		<entry>
		<title>
			MY QUALIFICATIONS
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/MY%20QUALIFICATIONS" />
		

		<id>@wiki::16/</id>
		<published>
			2007-03-20
			
		</published>
		<updated>
			2007-03-20T19:24:59Z
		</updated>
		
		
				
		<summary>
			EDUCATION

1: LLM. (Viva remaining)
Institution: Karachi University
Location: Karachi, Pakistan.
Completion Date: July 2001.
Degree, Major: Master’s Degree, Law (viva remaining)
Description: Major subjects were Shipping Laws, International Laws,

2: LLB.
Institution: Karachi University.
Location: Karachi, Pakistan.
Completion Date: May 1998.
Degree, Major: Professional Bachelor’s Degree, Law (2nd Division)
Description: Major subjects were Conveyance &amp; Pleading, Interpretation of Statutes, Arbitration Law, Law of Evidence, Limitation Law, Constitutional Remedies, Legal Ethics, Civil Procedure Code, Criminal Procedure code and Medical Jurisprudence.

3: BL.
Institution: Karachi University.
Location: Karachi, Pakistan.
Completion Date: June 1996.
Degree, Major: Bachelor’s Degree, Law ( 2nd Division)
Description: Major subjects studied were Contract Law, Sale of Goods Law, Company Laws, Negotiable Instruments Law, Partnership Law, Registration Law, Transfer of Property Law, Succession Law, International Law, Labor Law, Income Tax Law, Principles of Equity, Constitution of USA, Principles of British Constitution, Constitution of Pakistan, Law of Torts &amp; Easement, Trust Law, Specific Relief Law, Jurisprudence, Islamic Jurisprudence and Criminal Law.

4: SMIE (Civil)
Institution: Institute of Engineers, Pakistan.
Location: Karachi, Pakistan.
Since Date:  July 1977.
Degree, Major: Diploma in Civil Engineering.
Description: All Civil Engineering Subjects.

5: B.Com. 
Institution: Karachi University.
Location: Karachi, Pakistan.
Completion Date: July 1978.
Degree, Major: Bachelor’s Degree in Business Administration &amp; Commerce.
Description: Major subjects were Business Drafting, Accounting, Advance Accounting, Statistics, Auditing, Book Keeping, Business Law, Company Law, Income Tax Law and Labor Law.

6: MA (Mathematics)- continued
Institution: Karachi University.
Location: Karachi, Pakistan.
Registration Since: July 1977.
Degree, Major: Master’s Degree, Mathematics (continued).
Description: All mathematics subjects.

7: DHMS.
Institution: Pakistan Central Medical College &amp; Hospital, Karachi.
Location: Karachi, Pakistan.
Completion Date: April 1999.
Degree, Major: Diploma, Medical (Homeopathy)
Description: All Medical subjects studied in 4 years.

8: MSBC.
Institution: Sindh Bar Council.
Location: Karachi, Pakistan.
Completion Date: July 2002.
Degree, Major: Membership of Sindh Bar Council, Advocate on roll.
Description: Examined in all Law subjects.

9: F.Sc. (Mathematics)
Institution: Jinah College.
Location: Karachi, Pakistan.
Completion Date: June 1972.
Degree, Major: Certificate, Science with Mathematics.
Description: Major subjects in whom Examined is Mathematics, Physics &amp; Chemistry with Practicals. Subsequently Examined in Biology subjects with Practicals.

10: S.Sc. (Mathematics)
Institution: Aisha Bawany School.
Location: Karachi, Pakistan.
Completion Date: June 1970.
Degree, Major: Certificate, Science with Mathematics.
Description: Major subjects in whom Examined is Mathematics, Technical Drawing, Physics, and Chemistry with Practicals.
		</summary>
	</entry>
		<entry>
		<title>
			MY PROFESSIONAL EXPERIENCE
		</title>
		<link href="http://quantitysurveyor.atwiki.com/page/MY%20PROFESSIONAL%20EXPERIENCE" />
		

		<id>@wiki::15/</id>
		<published>
			2007-03-20
			
		</published>
		<updated>
			2007-03-20T23:37:12Z
		</updated>
		
		
				
		<summary>
			PROFESSIONAL EXPERIENCE

A: July 2002-Present:
SENIOR QUANTITY SURVEYOR
Ashfaq Associates (Private) Limited
Pakistan

RESPONSIBILITIES

01: Responsible for all Quantity Surveying, Estimating functions including:
02: Pre-tender &amp; Post-tender Contract Administration.
03: Active participation in Pre-Contract Negotiation.
03: Preparation Submission &amp; getting Approval Interim &amp; Final Bills.
04: Preparation Submission &amp; getting Approval of Claims &amp; Extra Items.
05:Timely advising project directors &amp; managers, actions regarding Contractual Obligations
06: Preparation, Submission &amp; getting Approval of all Finalization Documents including Contract Close Out Documents.
               07: Preparation, Submission &amp; getting Approval of Variation Orders.
08: Preparation &amp; getting Approval of Bar Bending Schedule.
09: Preparation of Ordinary &amp; Specialist Sub-Contracts.
10: Preparation of Contract Documents.
11: Take Off &amp; Estimating from Conceptual &amp; Working Drawings.
12: Take Off &amp; Estimation of Airport Projects, Runways, Taxiways, Aprons, Terminal Buildings, Royal Lounges, Parking &amp; External Developments, Up gradations of Runways, Taxiways &amp; Aprons, Hangers, Palaces, Garages, Residential Complexes, Hospitals, 
13: Takeoff &amp; Estimation of Refurbishment Works, Addition &amp; Alteration Works.
14: Calculating &amp; Indenting Construction Materials.
15: Checking &amp; Advising Corrections in Working / Execution Drawings.
16: Take off &amp; Estimation of Furniture’s &amp; Interiors.
17: Organizing Preparation of As built Drawings.
18: Drafting &amp; initiating all Contractual Correspondence.
19: Drafting letter for Extension of Time.
20: Participating in Design of Airport Projects.
21: Reconciliation of Materials.
22: Physical Measurement of Aggregates and other Materials at site,
23: Physical Measurements of works carried out.


B: April-1980 to June-2002
SENIOR QUANTITY SURVEYOR
MacDonald Layton &amp; Company (British Management)
Pakistan.

Recruited as Senior Quantity Surveyor, however the responsibilities gradually increased due to the introduction of following advanced Qualifications.
1: BL. A Graduate Degree In the faculty of Law, with Contract Law, 
2: LLB. A professional Graduate Degree in the faculty of Law.
3: LLM. A Master’s Degree in the faculty of Law (viva remaining)

RESPONSIBILITIES


01: Responsible for all Quantity Surveying, Estimating functions including:
02: Pre-tender &amp; Post-tender Contract Administration.
03: Preparation Submission &amp; getting Approval of Interim &amp; Final Bills.
04: Preparation Submission &amp; getting Approval of Claims &amp; Extra Items.
05:Timely advising project directors &amp; managers, actions regarding Contractual Obligations
06: Preparation, Submission &amp; getting Approval of all Finalization Documents.
               07: Preparation, Submission &amp; getting Approval of Variation Orders.
08: Preparation &amp; getting Approval of Bar Bending Schedule.
09: Preparation of Ordinary &amp; Specialist Sub-Contracts.
10: Preparation of Contract Documents.
11: Take Off &amp; Estimating from Conceptual &amp; Working Drawings.
12: Take Off &amp; Estimation of Power Projects, Sugar Mills, Salinity Control &amp; Reclamation Project, Residential Complexes, Roads,  
13: Takeoff &amp; Estimation of Refurbishment Works, Addition &amp; Alteration Works.
14: Calculating &amp; Indenting Construction Materials.
15: Checking &amp; Advising Corrections in Working / Execution Drawings.
16: Valuations.
17: Organizing Preparation of As built Drawings.
18: Drafting &amp; initiating all Contractual Correspondence.
19: Drafting letter for Extension of Time.
20: 01: Responsible for all Quantity Surveying, Estimating functions including:
02: Pre-tender &amp; Post-tender Contract Administration.
03: Preparation Submission &amp; getting Approval Interim &amp; Final Bills.
04: Preparation Submission &amp; getting Approval of Claims &amp; Extra Items.
05:Timely advising project directors &amp; managers, actions regarding Contractual Obligations
06: Preparation, Submission &amp; getting Approval of all Finalization Documents including Contract Close Out Documents.
               07: Preparation, Submission &amp; getting Approval of Variation Orders.
08: Preparation &amp; getting Approval of Bar Bending Schedule.
09: Preparation of Ordinary &amp; Specialist Sub-Contracts.
10: Preparation of Contract Documents.
11: Take Off &amp; Estimating from Conceptual &amp; Working Drawings.
12: Take Off for Billing purpose of Thermal Power Project, Security Printing Press, Sugar Mills, Embassy, Commercial Buildings, Sports Complex, Helipads, Salinity Control &amp; Reclamation project, Roads, Bridge, Shopping Centers, Restaurants, Industrial Projects, Residential Complexes, Hospitals, 5-Star Hotel.
13: Takeoff &amp; Estimation of Refurbishment Works, Addition &amp; Alteration Works.
14: Calculating &amp; Indenting Construction Materials.
15: Checking &amp; Advising Corrections in Working / Execution Drawings.
16: Take off &amp; Estimation of Furniture’s &amp; Interiors.
17: Organizing Preparation of As built Drawings.
18: Drafting &amp; initiating all Contractual Correspondence.
19: Drafting letter for Extension of Time.
20: Reconciliation of Materials.
21: Assisting Arbitration in Civil Engineering Contracts.
22: Coordinating with Company Lawyers in connection with the suits against Company.

C: January-1977 to August-1979
QUANTITY SURVEYOR
Zor Engineers Limited (British Management)
Pakistan.

RESPONSIBILITIES

1: Responsible for preparing &amp; submitting of Tenders for Civil Engineering Contracts.
2: Preparation Submission &amp; getting Approval Interim Bills.
3: Preparation, Submission &amp; getting Approval Claims and Extra Items.
4: Preparation &amp; getting Approval of steel Bar Bending Schedule.
5: Drafting Contractual Correspondence.
6: Computing &amp; Indenting Construction Materials.
7: Take off &amp; Estimation of Industrial Projects, Over head Tanks, Offices, Residential Buildings, Sports Complex, 
8: Computing &amp; Indenting Construction Materials.
9: Preparation of Sub-Contracts.
10: Preparation of Sub-Contractor’s Bills. 
11: Preparation of Bill of Quantities.
12: Other routine Quantity Surveying Functions.

D: June-1976 to December-1976
QUANTITY SURVEYOR 
Gulzar Builders-Pakistan

RESPONSIBILITIES

1: Responsible for part site supervision.
2: Sending daily, weekly &amp; monthly progress reports.
3: Preparation of Main &amp; Sub Contractor’s Bills.
4: Calculation of Construction Materials &amp; Indenting.
5: Other routine Quantity Surveying functions.

E: November-1975 to May-1976
QUANTITY SURVEYOR &amp; SITE INCHARGE
ASAN Associates-Pakistan

RESPONSIBILITIES

1: Responsible for over all site supervision on Shahnawaz Bhutto Memorial Library &amp; Jealous Bazaar Larkana.
2: Sending daily, weekly &amp; monthly progress reports.
3: Preparation of Main &amp; Sub Contractor’s Bills.
4: Calculation of Construction Materials &amp; Indenting.
5: Other routine Quantity Surveying functions

F: May- 1975 to October- 1975.
TRAINEE SUPERVISOR
Chawla Construction Company- Pakistan.

RESPONSIBILITIES

1: Labor Supervision.
2: Checking &amp; Measuring Construction Materials.
3: Reporting Daily Progress.